SINGLE FAMILY RESIDENTIAL

Cobblestone Tract 32836 – Moreno Valley, CA
Beazer Homes
Production precise grading, model precise grading, two park sites,  retaining walls and disclosure exhibits for 125 single family detached homes.

Golden Fields Tract 32834 – Moreno Valley, CA
Beazer Homes
Production precise grading, model precise grading, a park site, horse staging area, recreation trail, easement dedications, lot exhibits and retaining walls for 200 single family detached homes.

Bernal Residence – San Clemente, CA
Robert and Ann Bernal
Minor Exception Permit plan and processing for variance on detached garage / deck for single family residence.

Tract 32869 – Indio, CA
Beazer Homes
Site plan, model and production precise grading, retaining walls, storm drain arched-culvert, composite utility plans, lot disclosure and builder exhibits for 238 single family detached lots.

Lot 11-13 of Block 23 – City of Perris, CA
Classic Pacific Homes
Zone change and general plan amendment for 3 single family parcels.

Cantalena – Menifee, CA
Fieldstone Communities
Plotting studies for three single family detached tracts in the Cantalena Master Planned community.

Summerly Phase 1 Improvement Plans – City of Lake Elsinore, CA
Wilson Mikami Corporation (John Laing Homes)
Street, storm drain, sewer and water improvements including hydrology and hydraulics for 405 single family detached lots in five tracts.   Site plans for two- 74 unit tracts and peer review for backbone grading plans.

Barcelona Tract 32411 – Indio, CA
Beazer Homes
Site plan, model and production precise grading, retaining walls, storm drain culvert, composite utility plans, lot disclosure and builder exhibits for 136 single family detached lots.

Tract 17760– Fontana, CA
Fieldstone Communities
Due diligence and plotting studies for 30 single family detached residences

Tract 32997 – Riverside, CA
Beazer Homes
ALTA survey for financing purposes.

Moreno Valley 27 – Moreno Valley, CA
Beazer Homes
Site plan / lotting studies on a 27 acre site for single family lots.

Riverside Stockpile plan – Riverside, CA
Granite Equities
Stockpile permit plan for 37,000 cy stockpile, including NPDES processing.

San Jacinto Plot Plan – San Jacinto, CA
Wilson Mikami Corporation (Meritage Homes)
Site plan plotting study for 131 single family detached lots.

Summerly Phase 2 – Lake Elsinore, CA
Wilson Mikami Corporation (John Laing Homes)
Peer review for backbone rough grading plans for 11 single family detached tracts.

Blenheim Farms Lot Line Adjustment – San Juan Capistrano, CA
Civic Solutions, Inc.
Preparation of a lot line adjustment for two parcels in San Juan Capistrano, including a boundary survey and a record of survey.

French Valley Lotting Study – Temecula, CA
Granite Equities
Lotting study for 22 single family detached residential lots.

Verdemont Boundary Analysis – San Bernardino, CA
Beazer Homes
Peer review boundary analysis for parcel in San Bernardino, CA

Wildomar  - Wildomar, CA
Beazer Homes
Grading exhibits for project boundary condition with existing lots for project alternatives.  Survey of existing flood control channel and design exhibits for a 9 -  6’x 15’ concrete box structure drainage facility.  Prepare exhibits for FEMA submittal.

Menifee Farms II – Menifee, CA
Granite Equities
Tentative Map, preliminary hydrology, water quality management plan, and secondary access plan for a 28 lot single family detached tract.

Basement Design Task Force – Irvine, CA
Fieldstone Communities
Studies for opportunities and constraints for the construction of basements for single family production units in California.

Menifee Farms I – Menifee, CA
Granite Equities
Preliminary design review for sewer, storm drain and water improvements, as well as a storm drain channel street undercrossing.

Blenheim Farms Access Studies – San Juan Capistrano, CA
Civic Solutions, Inc.
Gated entry access study alternatives for the primary and secondary entrances for the parcel for review by the City of San Juan Capistrano in conjunction with the zone change application.

Boxwood Avenue – Fontana, CA
Spectra Homes
Field survey topography, entitlements and final engineering for 8 single family residential lots in Fontana.  The scope of work includes the tentative map, site plan,  rough grading, precise grading, street improvements, sewer, water and storm drain improvements, final tract map and survey.

Nishiyama Property – Anaheim, CA
John Laing Homes
Field survey topography, entitlements and final engineering for 45 single family detached condominium residential units in Anaheim.  The scope of work includes the tentative map, site plan,  rough grading, precise grading, street improvements, sewer, water and storm drain improvements, final tract map, condominium plans and survey.

Site Drive Property – Brea, CA
John Laing Homes
Field survey topography, entitlements and preliminary engineering for 51 single family detached lots in Brea, CA.  The scope of work includes lotting studies,  the tentative map, site plan, preliminary grading and utilities, fire master plan, boundary survey, topographic survey and an ALTA.

Shady Canyon Water Meter – Irvine, CA
Kennedy Pipeline
Prepare domestic water and reclaimed water improvement plans for the relocation of existing water services for a single family residence in Shady Canyon.

Rebuilding Together Home Make over – Los Angeles, CA
Sares-Regis Group
Field survey topography and engineering support services for a non-profit home make-over for a single family home in Los Angeles.  All services were donated.

Woodbury East, Arboleda
John Laing Homes
Site plan preparation and feasibility study for a single family development within the Woodbury East project in Irvine.

MULT-FAMILY RESIDENTIAL

Westgate Pasadena  Condominiums – Pasadena, CA
Sares Regis Group
Tentative Map and Site Plan Entitlement process for 3 Blocks of Condominiums, Apartments and Commercial buildings.  Block 1 is 88 condo units and retail, block 2 is 252 condo units with retail, and block 3 is 480 condo units.  All three blocks are podium level construction over two levels of underground parking.  Final engineering for the all three blocks including demolition, preliminary grading, off-site street improvements, sewer, water and storm drain improvements, and topographic survey.  This project will be LEED certified with the US Green Building Council.

Westgate Pasadena  Condominiums (Block 3) – Pasadena, CA
Sares Regis Group
Final engineering for the Block 3 project including rough grading, shoring,  precise grading, street improvements, on-site sewer, water and storm drain improvements, final tract map and survey for 480 condominium units, a park, recreation center and landscaped courtyards.  The project consists of 4 levels of residential units over 2 levels of underground parking.  This project will be LEED certified with the US Green Building Council.

The Crossing Apartments, Anaheim, CA
Sares Regis Group
Tentative Map and Site Plan Entitlement process 312 Apartments and 39 live/ work units in Anaheim.  Final engineering for the project including rough grading, shoring,  precise grading, street improvements, on-site sewer, water and storm drain improvements, final tract map and survey for the podium construction project.  The project consists of 4 levels of residential units over 2 levels of underground parking, with one additional on-grade residential building.  This project will be LEED certified with the US Green Building Council.

Villa Dorado Apartments – San Diego, CA
The Irvine Company Apartment Communities
Field survey topography and aerial topography for a 25 acre existing apartment complex in San Diego for the preparation of digital base maps that will be utilized for new landscape amenities for the site.  Precise grading plans for a new project gated entry, two recreation centers and miscellaneous ADA code compliance improvements.

The Lakes Apartments – Costa Mesa, CA
LandArcWest
Field survey topography and aerial topography for an  existing apartment complex in Costa Mesa for the preparation of digital base maps that will be utilized for new landscape amenities for the site.  Precise grading, drainage and demolition plans for a new gated entrance, recreation centers, landscape amenities and interior podium atriums throughout the project.

Westgate Pasadena  Condominiums (Block 2) – Pasadena, CA
Sares Regis Group
Final engineering for the Block 2 project including rough grading, shoring,  precise grading, street improvements, on-site sewer, water and storm drain improvements, final tract map and survey for 252 condominium units, a park, recreation center and landscaped courtyards.  The project consists of 4 levels of residential units over 2 levels of underground parking.  This project will be LEED certified with the US Green Building Council.

Malibu Canyon Apartments – Calabasas, CA
AIMCO
Field survey topography and final engineering for a 55 Acre existing apartment complex in Calabasas, CA.  The scope of work includes schematic design, precise grading and improvements and topographic survey for 9 areas within the site includes 5 recreation pool areas and 4 entries.

Asante Villas  Condominiums– Moreno Valley, CA
A & W Builders
Field survey topography for an existing apartment complex in Moreno Valley.  Final engineering for the conversion of the apartment complex to  147 condominiums including the construction of new buildings, a recreation center and gated entries. The plans scope of work includes demolition,  rough grading, precise grading, street improvements, sewer, water and storm drain improvements, final tract map and survey.

Metropolis Podium Condominiums / Wrap Apartments – Irvine, CA
Sares-Regis Group
General Plan Amendment / Zone Change site plans, Master Plan / site plan, tentative map, fire master plan, preliminary grading, utilities, boundary survey and topography for the 7 acre urban infill project for a four over two podium level condominium building with a recreation center and a four level wrap type apartment building with a recreation center and parking structure.

Marguerite Gardens – Alhambra, CA
California P.E.O. Homes
Tentative Map and Site Plan Entitlement process for a 3.5 acres site consisting approximately 240 senior living units in Alhambra, CA.  Final engineering for the project including rough grading, shoring,  precise grading, podium penetrations,  street improvements, on-site sewer, water and storm drain improvements, final tract map, topographic survey, ALTA and survey for the podium construction project.  The project consists of 3 to 5 levels of residential units over 1 level of underground parking. 

Westgate Pasadena  Condominiums (Block 1) – Pasadena, CA
Sares Regis Group
Final engineering for the Block 1 project including rough grading, shoring,  precise grading, podium penetrations, street improvements, on-site sewer, water and storm drain improvements, final tract map and survey for 88 condominium units and first level retail space.  The project consists of 4 levels of residential units, over 1 level retail space, over 2 levels of underground parking.  This project will be LEED certified with the US Green Building Council and an existing historic building will be protected within the project site.

The Acres Apartments – Escondido, CA
LandArcWest
Field survey topography and aerial topography for an existing apartment complex in Escondido for the preparation of digital base maps that will be utilized for new landscape amenities for the site.  Precise grading, drainage and demolition plans for a new entry, recreation / pool facilities, landscape amenities throughout the project.

Atria Golden Creek – Irvine, CA
Atria Senior Living Group
Topographic survey and preparation of precise grading plans for a new vehicular entrance and 3 exterior courtyard areas, including fountains, fire places and other amenities.

Atria Los Posas – Camarillo, CA
Atria Senior Living Group
Topographic survey and preparation of precise grading plans for the new Life Guidance wing, and front fire place patio and a sunken atrium courtyard.

Piazza Las Tunas, Temple City, CA
A &W Builders
Peer review for the civil engineering portion of the project for a 3.7 Acre Condominium and Retail Podium Construction project in Temple City, CA.  Attend team meetings, review engineering plans and provide plan check comments to the engineer of record.  Prepare an ALTA survey of the site to verify site boundary and constraints for the owner.

The Village at Rolling Hills Estates, Rolling Hills Estates, CA
Sares Regis Group
Tentative Map and Site Plan Entitlement process for a 3.3 acres site consisting of  69 Condominium units and 68,000 square feet of retail in Rolling Hills Estates, CA .  Final engineering for the project including rough grading, shoring,  precise grading, podium penetrations,  street improvements, on-site sewer, water and storm drain improvements, final tract map, topographic survey, ALTA and survey for the podium construction project.  The project consists of 3 to 5 levels of residential units over 1 level of retail over 3 levels of underground parking.  This project will be LEED certified with the US Green Building Council.

Tract 30394 – Murrieta, CA
Beazer Homes
Site plan and plotting studies for multi-family attached condominium project.

Stonegate  Apartment Site 2 – Irvine, CA
The Irvine Company Apartment Communities
Site planning, preliminary grading and utilities, and project entitlement for 315 apartment units and a recreation center.

Holland Road Site Plan – Temecula, CA
D.R. Horton
Site plan and plotting studies for  66 single family detached homes and 238 multi-family tri-plex condominiums and a recreation center.

Hillcreste Apartments – Los Angeles, CA
LandArcWest
Street improvements, sewer and water improvements and precise grading plans for a new entrance street and water feature.  Survey topography of existing site conditions.

Monrovia Avenue Condominiums- Costa Mesa, CA
John Laing Homes
Due diligence research and feasibility study for 90 attached condominium units for an industrial zoned overlay district in Costa Mesa.

Lago de San Marcos – San Marcos, CA
D.R. Horton
Preliminary cost estimate for 42 multi family attached condominium unit site.

Windrift Apartments – Oceanside, CA
AIMCO
Coordinate geotechnical services and site analysis for ground water conditions on site.

RECREATION PROJECTS

Woodbury Parks – Irvine, CA
Clark and Green Associate, Landscape Architects
Technical support and review services for two parks in Woodbury.

Orchard Hills Lot 6 Private Park – Irvine, CA
EPT Design
Precise grading and utilities for a 3.8 AC pool park

Stonegate Lot 21 Public Park – Irvine, CA
Clark and Green Landscape Architects
Precise grading and utilities for a 6 AC public park facility.

Club Laguna Apartments -  Aliso Viejo, CA
LandArcWest
Survey topography and mapping  for an existing recreation center, and civil engineering support services for the landscape architecture construction documents.

Chapman University Day Care Center – Orange, CA
Chapman University
Field survey topography, and final engineering for two playground areas at the child care center, including off-site parking analysis and improvements.  The scope of work includes the precise grading plans and survey.

 Sunset Ridge Park – Newport Beach, CA
EPT Design
Field survey topography, aerial topography and preliminary engineering support services  for a 13 acre proposed public park in Newport Beach.  Provide preliminary grading and utility concepts for the landscape architect.

Shady Canyon Trail Head – Irvine, CA
EPT Design
Field survey topography and precise grading plans for a new walkway, sculpture garden and parking spaces for an existing trail head and horse staging area in Quail Hill

Newport Beach Cemetery – Newport Beach, CA
Clark and Green Associates
Water quality management plans and hydrology studies for grading operations at the cemetery.

Lake Forrest Arbors Apartments
LandArcWest.
Field survey topography for an existing recreation area within an existing apartment complex in Lake Forrest for the preparation of digital base maps that will be utilized for new landscape amenities for the site.  Precise grading, drainage and demolition plans for a recreation / pool facility and landscape amenities throughout the project.

COMMERCIAL PROJECTS

Long Beach Emergency Center -  Long Beach, CA
LPA, Inc. / Capital Group
Field topographic survey and mapping, precise grading, drainage, and demolition plans for an existing building, parking lot and parking structure in Long Beach as required for conversion of the existing structure to a City operated facility.

Fresh and Easy Distribution Facility, Moreno Valley, CA
ESA
Prepare sewer, water, storm drain, hydrology and water quality feasibility studies for the EIR process for the second phase of the distribution center at the March Business Center.

Twin Peaks Commercial Center – Lake Forest, CA
Kelly Capital
Land planning studies for existing commercial center and parking lot.

Fullerton Land Study – Fullerton, CA
Kelly Capital
Land planning studies for commercial / industrial site.

Redhill Avenue Topography and ADA Design -  Tustin, CA
LPA, Inc.
Survey for an existing parking lot and front entry access ramp of an existing commercial building in Tustin.  Analyzed the survey information and prepared ADA compliant grading exhibits for the architects.

Fox Studios Artist Garden  - Los Angeles, CA
Valley Crest
Precise grading, drainage, and demolition plans for an Artist Garden on the Fox Studio Lot.

PUBLIC WORKS PROJECTS

Wildomar Culvert Crossing  - Wildomar, CA
Beazer Homes
Prepare Flood Control Box Culvert designs for 10 – 7’x14’ box  culverts to be constructed beneath an existing road as required to improve an existing flood control channel.  Prepare rough grading, street improvements, sewer and water improvements for the affected existing utilities that need to be relocated or improved.

Sunshine Canyon Landfill Irrigation Plan – Riverside, CA
Natures Image, Inc.
Preparation of a conceptual landscape irrigation master plan for three reclaimed areas of a landfill.

Quail Hill Irrigation Service, Irvine, CA
Manassero Farms
Reclaimed water improvement plans for two new irrigation services on an existing 36” steel reclaimed water mainline.

Indiana Avenue Traffic Control – Riverside, CA
EBS, Inc.
Traffic control plans for street paving operation in Riverside.

Hollywood Apartments Traffic Control – Hollywood, CA
Sares-Regis Group
Traffic control plans for street paving and utility installation in Hollywood.

Anaheim Apartments Traffic Control – Anaheim, CA
John Laing Homes
Traffic control plans for street paving and utility installation in Anaheim.

Citrus Avenue Traffic Control – Fontana, CA
EBS, Inc.
Traffic control plans for street paving operation in Fontana.

Murrieta Traffic Control – Murrieta, CA
EBS, Inc.
Traffic control plans for street paving operation in Murrieta.

Lake Elsinore Traffic Control – Lake Elsinore, CA
EBS, Inc.
Traffic control plans for street paving operation in Lake Elsinore.

Buena Park Traffic Control – Buena Park, CA
EBS, Inc.
Traffic control plans for street paving operation in Buena Park.

Main Street Project, Riverside, CA
EBS, Inc.
Review SWPPP for compliance with standards.

4th Street Traffic Control, Riverside, CA
EBS, Inc.
Traffic control plans for street paving operation in Riverside.

Main Street Traffic Control, Riverside, CA
EBS, Inc.
Traffic control plans for street paving operation in Riverside.

Anaheim-La Palma Detour Plan
EBS, Inc.
Traffic control plans for street paving operation in Anaheim.

Navajo Road Traffic Control, Victorville, CA
EBS, Inc.
Traffic control plans for street paving operation in Victorville.

QUALIFIED